Construction Progress of Part B Singapore Police Coast Guard Pier Project-Aluminum Pontoon

Time:2017-05-09 Click:3642
           After completion of Phase A of the Singapore Police Coast Guard Pier project and a formal handover, the vessels that were originally in harbor Phase B are being transferred and docked in the Phase A harbor.

On 30 April 2017, our construction workers were onsite to perform the piling and installation works. Onsite pontoon assembly, launching the bridge in water, installation of oil and other equipment, such as machinery and pipeline work, & other works are in progress and orderly being carried out.